Business, 20.03.2020 09:50 shauntleaning
It costs $75 per day for each day that a construction crew is on site. The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity. Use this information to determine the lowest cost for this project. All times given are in days. Activity Predecessor TUOL Ontol Normal Minimum Crash Cost Time Time |$/day) 10 16 $70 16 3 $40 2 2 - 4 2 $60 $80 8 15 ($90 ONNA C 1 DE
a.$1,750
b.$1,720
c.$1,810
d.$1,780
Answers: 1
Business, 23.06.2019 02:00
When the two countries did not specialize, the total production of jeans was 23 million pairs per month, and the total production of corn was 68 million bushels per month. because of specialization, the total production of jeans has increased by million pairs per month, and the total production of corn has increased by million bushels per month. because the two countries produce more jeans and more corn under specialization, each country is able to gain from trade?
Answers: 1
Business, 23.06.2019 12:50
In a "dutch auction" for new stock, individual investors place bids for shares directly. each potential bidder indicates the price he or she is willing to pay and how many shares he or she will purchase at that price. the highest price that permits the company to sell all the shares it wants to sell is determined, and this is the "market clearing price." all bidders who specified this price or higher are allowed to purchase their shares at the market clearing price. true false
Answers: 2
It costs $75 per day for each day that a construction crew is on site. The project manager determine...
Biology, 10.12.2019 02:31
Mathematics, 10.12.2019 02:31
Mathematics, 10.12.2019 02:31
English, 10.12.2019 02:31
History, 10.12.2019 02:31
History, 10.12.2019 02:31
History, 10.12.2019 02:31
Mathematics, 10.12.2019 02:31
Mathematics, 10.12.2019 02:31
Mathematics, 10.12.2019 02:31
Mathematics, 10.12.2019 02:31
History, 10.12.2019 02:31
History, 10.12.2019 02:31