Mathematics, 18.06.2021 14:20 wilkinsserrano3

Network analysis activity preceded by duration days
A - 8
B - 5
C - 3
D A 5
E A 6
F B, G 6
G A, C 3
H A, C 10
I D 8
J E, F,H 12
K E, F,H 11