Mathematics, 06.01.2021 14:00 nashaflores17

24 men working at 8 hours perday can do a piece of work in 15 day. in how many days can 20 men working at 9 hours day can complete the same work?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 16:50
If m 17 27 90 63 ** picture is attached
Answers: 1
question
Mathematics, 21.06.2019 17:30
Hello can you me find all the products
Answers: 1
question
Mathematics, 21.06.2019 21:00
Julie buys 2kg of apples and 7kg of pears ? 12.70. the pears cost ? 1.30 per kilogram what is the price per kilogram of the apples? show your working out
Answers: 2
question
Mathematics, 21.06.2019 21:50
What is the 17th term in the arithmetic sequence in which a6 is 101 and a9 is 83
Answers: 3
You know the right answer?
24 men working at 8 hours perday can do a piece of work in 15 day. in how many days can 20 men worki...
Questions
question
Mathematics, 24.03.2020 05:34
question
Mathematics, 24.03.2020 05:34
question
Mathematics, 24.03.2020 05:34
question
Mathematics, 24.03.2020 05:35
Questions on the website: 13722361