In this assignment, your team is managing a software development project with a total project budget of $178,500. Total work effort is 1,536 hours and the timeline for completion 24 weeks. At the end of week 12, the plan was to have completed 55% of the project scope. However, actual progress was calculated at 650 worth of hours completed on project activities and actual cost (in hours) for these activities is 780. With your team, please answer the following questions. For each response, show the pertinent formula(s) as it applies and "show your work" in addition to providing a narrative statement.
a. How much money was supposed to have been spent at the end of week 12?b. Will the project finish on time and within the given budget?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
What is the prime factorization of 195
Answers: 2
question
Mathematics, 21.06.2019 17:30
Mickey needs to cut pieces of ribbon that are each 1 meter long tie onto balloons. if he has 8 pieces of ribbon that are each 1 dekameter long. how many 1 meter pieces of ribbon can he cut
Answers: 1
question
Mathematics, 21.06.2019 18:00
Aman is 6 feet 3 inches tall. the top of his shadow touches a fire hydrant that is 13 feet 6 inches away. what is the angle of elevation from the base of the fire hydrant to the top of the man's head?
Answers: 1
question
Mathematics, 21.06.2019 20:30
Which expression demonstrates the use of the commutative property of addition in the first step of simplifying the expression (-1+i)+(21+5i)+0
Answers: 2
You know the right answer?
In this assignment, your team is managing a software development project with a total project budget...
Questions
question
Arts, 13.10.2019 01:30
question
Mathematics, 13.10.2019 01:30
Questions on the website: 13722367