Agroup of 9 workers was assigned to paint the walls in a house, which could be completed in 48 hours. however, after working 8 hours, some of the workers left the group and the remaining workers could complete the job in 72 hours. how many workers left the team?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
Which expression is equivalent to 8(k + m) − 15(2k + 5m)?
Answers: 1
question
Mathematics, 21.06.2019 17:50
Segment ab is shown on the graph. which shows how to find the x-coordinate of the point that will divide ab into a 2: 3 ratio using the formula
Answers: 2
question
Mathematics, 21.06.2019 21:00
Deepak plotted these points on the number line. point a: –0.3 point b: – 3 4 point c: – 11 4 point d: –0.7 which point did he plot incorrectly?
Answers: 2
question
Mathematics, 21.06.2019 21:00
Need match the functions with correct transformation. f(x) = -3x f(x) = |x-1|+3 f(x) = √(x+3) 1/2x² f(x) = (x+1)²-3 4|x| 1. compress by a factor of 1/2 2. stretch by a factor of 4 3. shift to the left 3 4. shift to the left 1 5. shift up 3 6. reflection
Answers: 1
You know the right answer?
Agroup of 9 workers was assigned to paint the walls in a house, which could be completed in 48 hours...
Questions
Questions on the website: 13722363