Each of 10 machines works at the same constant rate doing a certain job. the amount of time needed by the 10 machines, working together, to complete the job is 16 hours.
how many hours would be needed if only 8 machines, working together, were used to complete the job?

a. 18
b. 20
c. 22
d. 24
e. 26

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 20:30
What is the length of the segment, endpoints of which are intersections of parabolas y=x2? 11 4 x? 7 4 and y=? 7 8 x2+x+ 31 8 ?
Answers: 2
question
Mathematics, 21.06.2019 22:00
The two box p digram the two box plots show the data of the pitches thrown by two pitchers throughout the season. which statement is correct? check all that apply. pitcher 1 has a symmetric data set. pitcher 1 does not have a symmetric data set. pitcher 2 has a symmetric data set. pitcher 2 does not have a symmetric data set. pitcher 2 has the greater variation.ots represent the total number of touchdowns two quarterbacks threw in 10 seasons of play
Answers: 1
question
Mathematics, 21.06.2019 22:30
Kevin's bank offered him a 4.5% interest rate for his mortgage. if he purchases 3 points, what will be his new rate?
Answers: 2
question
Mathematics, 22.06.2019 00:10
Change negative exponents to positive, then solve
Answers: 1
You know the right answer?
Each of 10 machines works at the same constant rate doing a certain job. the amount of time needed b...
Questions
question
Biology, 07.06.2021 18:00
question
Mathematics, 07.06.2021 18:00
question
English, 07.06.2021 18:00
question
Mathematics, 07.06.2021 18:00
question
Mathematics, 07.06.2021 18:00
question
English, 07.06.2021 18:00
Questions on the website: 13722359