Each x requires 2 of component y; each y requires 4 of part z. the lead time for assembly of x is 1 week. the lead time for the manufacture of y is 1 week. the lead time for the procurement of z is 6 weeks. the cumulative lead time for x is weeks.
a. 48
b. 7
c. 8
d. 10

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 13:10
Anthony is making a collage for his art class my picking shapes randomly. he has five squares, two triangles, two ovals, and four circles. find p( circle is chosen first)
Answers: 1
question
Mathematics, 21.06.2019 18:00
Need on this geometry question. explain how you did it.
Answers: 2
question
Mathematics, 21.06.2019 19:30
The pyramid below was dissected by a horizontal plane which shape describes the pyramid horizontal cross section
Answers: 1
question
Mathematics, 21.06.2019 20:30
Find the solution(s) to the system of equations. select all that apply y=x^2-1 y=2x-2
Answers: 2
You know the right answer?
Each x requires 2 of component y; each y requires 4 of part z. the lead time for assembly of x is 1...
Questions
question
Mathematics, 09.04.2020 00:29
question
Mathematics, 09.04.2020 00:29
question
Mathematics, 09.04.2020 00:29
Questions on the website: 13722367