A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

Please answer and thank you

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 23:30
What are listed in the vertical columns across the top of the event editor? a. file names b. conditions c. check marks d. action types
Answers: 1
question
Computers and Technology, 23.06.2019 04:31
Selling a product through an electronic medium is
Answers: 1
question
Computers and Technology, 23.06.2019 08:00
What is a scenario where records stored in a computer frequently need to be checked
Answers: 2
question
Computers and Technology, 23.06.2019 18:50
What is transmission control protocol/internet protocol (tcp/ip)? software that prevents direct communication between a sending and receiving computer and is used to monitor packets for security reasons a standard that specifies the format of data as well as the rules to be followed during transmission a simple network protocol that allows the transfer of files between two computers on the internet a standard internet protocol that provides the technical foundation for the public internet as well as for large numbers of private networks
Answers: 2
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Social Studies, 04.10.2020 18:01
question
Social Studies, 04.10.2020 18:01
question
Mathematics, 04.10.2020 18:01
question
Mathematics, 04.10.2020 18:01
Questions on the website: 13722362