subject
Business, 24.12.2021 07:40 MansellS6756

An activity on a project has Earliest Start Time (EST) of 14 days, Latest Completion Time (LCT) of 29 days. If the activity has the duration of 10 days, what is the Slack for this activity

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 15:30
In 2015, lori assigned a paid-up whole life insurance policy to an irrevocable life insurance trust (ilit) for the benefit of her three children. the ilit contained a crummey provision for the benefit of each child. at the time of the transfer, the whole life insurance policy was valued at $200,000, and since lori had not made any other taxable gifts during her lifetime, she did not owe any gift tax. lori died in 2016, and the face value of the whole life insurance policy of $2,000,000 was paid to the ilit. regarding this transfer, how much is included in lori’s gross estate at her death?
Answers: 1
question
Business, 22.06.2019 16:50
Identify and describe a variety of performance rating scales that can be used in organizations including graphical scales, letter scales, and numeric scales.
Answers: 2
question
Business, 22.06.2019 19:40
Sue now has $125. how much would she have after 8 years if she leaves it invested at 8.5% with annual compounding? a. $205.83b. $216.67c. $228.07d. $240.08e. $252.08
Answers: 1
question
Business, 22.06.2019 19:50
Managers in a firm hired to improve the firm's profitability and ultimately the shareholders' value will add to the overall costs if they pursue their own self-interests. what does this best illustrate? a. diseconomies of scale b. principal-agent problem c. experience-curveeffects d. information asymmetries
Answers: 1
You know the right answer?
An activity on a project has Earliest Start Time (EST) of 14 days, Latest Completion Time (LCT) of 2...