Match Point, Inc. has the following overhead standards:
Variable overhead: 4 hours at $8 per hour
Fixed overhead: 4 hours at $10 per hour

The standards were based on a planned activity of 20,000 machine hours when 5,000 units were scheduled for production. Actual data follow:

Variable overhead incurred: $167,750
Fixed overhead incurred: $210,000
Machine hours worked: 19,800
Actual units produced: 5,100

Draco's fixed-overhead budget variance is:

a. $6,000 unfavorable.

b. $7,000 unfavorable.

c. $10,000 unfavorable.

d. $12,000 unfavorable.

e. None of the other answers are correct.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 22:50
Which of the following statements is true? a job costing system will have a separate work in process account for each of the major processes. a process costing system will have a single work in process account. a process costing system will have a separate raw materials account for each of the major processes. a process costing system will have a separate work in process account for each of the major processes.
Answers: 3
question
Business, 22.06.2019 09:00
Drag the tiles to the correct boxes to complete the pairs.(there's not just one answer)match each online banking security practice with the pci security requirement that mandates it.1. encrypting transfer of card data2. installing a firewall3. installing antivirus software4. assigning unique ids and user namesa. vulnerability management programb. credit card data protectionc. strong access controlsd. secure network
Answers: 3
question
Business, 22.06.2019 22:00
Acontractor was awarded a purchase order for commercial items for $1.5 million under the authority of far subpart 13.5. the purchase order was issued in november 2010 and containedall applicable clauses that were current as of the date of the purchase order. under the purchase order, the contractor is required to comply with a small business subcontracting plan that contains all of the required elements. which of the following is true? a.the contractor must submit a standard form 294, subcontracting report for individual contracts. b.the contractor must submit an individual subcontracting report through the electronic subcontracting reporting system (esrs). c.the contractor may submit either an sf 294 or report its subcontracting through esrs. d.the contractor is not required to submit any subcontracting reports.
Answers: 1
question
Business, 22.06.2019 23:00
Which completes the equation? o + a + consideration (+ = k legal capacity legal capability legal injunction legal corporation
Answers: 1
You know the right answer?
Match Point, Inc. has the following overhead standards:
Variable overhead: 4 hours at $8 per...
Questions
question
Mathematics, 16.01.2020 07:31
question
Mathematics, 16.01.2020 07:31
question
Mathematics, 16.01.2020 07:31
question
Mathematics, 16.01.2020 07:31
Questions on the website: 13722367