Meghan's team is comprised of 10 people who work 40 hours per week.
The team is tasked with completing a project that requires 700 man-hours
in one week. To complete the project, Meghan plans to add n members to
the team and have each team member work an extra 3n hours that week.
What is the minimum number of extra team members she needs?
Answers: 2
SAT, 23.06.2019 15:10
Which is an advantage to using nonrenewable resources? a. they can be cheaper. b.they can have a lower impact on the environment. c.they can be used up rapidly. d.they can contribute to global warming.
Answers: 1
SAT, 26.06.2019 01:30
What are the three stages of volcanic activity? a. active, magma, lava c. extinct, eruption, explosive b. eruption, quiet, explosive d. active, dormant, extinct
Answers: 1
SAT, 26.06.2019 13:00
Rick is on a bicycle trip. every 4 days he bikes 230 km. if rick keeps this same pace for 16 days, how many kilometers will he bike?
Answers: 1
Meghan's team is comprised of 10 people who work 40 hours per week.
The team is tasked with complet...
Mathematics, 02.09.2020 23:01
Social Studies, 02.09.2020 23:01
Mathematics, 02.09.2020 23:01
Mathematics, 02.09.2020 23:01
English, 02.09.2020 23:01
Mathematics, 02.09.2020 23:01