(Unitary Method)
12 workers can do a piece of work in 20 days. How many workers should be added to complete the work in 16 days?
(Give answer in process by process)
(Answer is 3 workers)
Answers: 3
Mathematics, 21.06.2019 15:10
Aboat's value over time is given as the function f(x) and graphed below. use a(x) = 400(b)x + 0 as the parent function. which graph shows the boat's value increasing at a rate of 25% per year?
Answers: 3
Mathematics, 21.06.2019 18:00
Kayla has a $500 budget for the school party.she paid $150 for the decorations.food will cost $5.50 per student. what inequality represents the number of students,s, that can attend the party?
Answers: 1
Mathematics, 21.06.2019 21:30
Consider the following equation. 1/2x^3+x-7=-3sqrtx-1 approximate the solution to the equation using three iterations of successive approximation. use the graph below as a starting point. a. b. c. d.
Answers: 3
(Unitary Method)
12 workers can do a piece of work in 20 days. How many workers should be added to...
English, 26.10.2020 20:40
Mathematics, 26.10.2020 20:40
Mathematics, 26.10.2020 20:40
English, 26.10.2020 20:40
Geography, 26.10.2020 20:40
Business, 26.10.2020 20:40
Mathematics, 26.10.2020 20:40
Mathematics, 26.10.2020 20:40
Social Studies, 26.10.2020 20:40
Social Studies, 26.10.2020 20:40