Mathematics, 04.01.2022 01:00 victoria1831

6 labour complete a work in 12 days. How many labours should added to complete the works in 8 days?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 20:30
Find the value of x for which line a is parallel to line b
Answers: 1
question
Mathematics, 22.06.2019 02:00
Mariano delivers newspaper. he always puts 3/4 of his weekly earnings in his savings account and then divides the rest equally into 3 piggy banks for spending at the snack shop, the arcade and the subway
Answers: 2
question
Mathematics, 22.06.2019 02:30
Which statement best explains whether the table represents a linear or nonlinear function? input (x) output (y) 2 5 4 10 6 15 8 20 it is a linear function because the input values are increasing. it is a nonlinear function because the output values are increasing. it is a linear function because there is a constant rate of change in both the input and output. it is a nonlinear function because there is a constant rate of change in both the input and output.
Answers: 3
question
Mathematics, 22.06.2019 03:50
Question 2 of 102 pointsthe temperature is 45°f. the temperature will decrease by 2°f each hour. leth be the number of hours.when will the temperature be below 32°f? write an inequality for this problem.oa. 45 + 2h 32b. 45 + 2h< 32o c. 45 - 2h< 32od. 45 - 2hs 32
Answers: 2
You know the right answer?
6 labour complete a work in 12 days. How many labours should added to complete the works in 8 days?...
Questions
question
Mathematics, 22.02.2021 01:10
question
Mathematics, 22.02.2021 01:10
question
Mathematics, 22.02.2021 01:10
question
Mathematics, 22.02.2021 01:10
Questions on the website: 13722360