Jing did 1/7 of a task in 3 days. How long will she take to do the whole task? Assume that she works the same rate over the entire period? 7 days
14 days
21 days
28 days

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 16:00
The equation x2 – 1x – 90 = 0 has solutions {a, b}. what is a + b?
Answers: 1
question
Mathematics, 21.06.2019 18:30
Select 2 statements that are true about the equation y+6=-10(x-3).1) the slope of the line is -102) the slope of the line is 33) one point on the line is (3,6)4) one point on the line is (3,-6)
Answers: 1
question
Mathematics, 21.06.2019 19:30
Evaluate the expression. (9 + 5)(3 + 2)0
Answers: 1
question
Mathematics, 21.06.2019 23:00
According to a study conducted in 2015, 18% of shoppers said that they prefer to buy generic instead of name-brand products. suppose that in a recent sample of 1500 shoppers, 315 stated that they prefer to buy generic instead of name-brand products. at a 5% significance level, can you conclude that the proportion of all shoppers who currently prefer to buy generic instead of name-brand products is higher than .18? use both the p-value and the critical-value approaches.
Answers: 1
You know the right answer?
Jing did 1/7 of a task in 3 days. How long will she take to do the whole task? Assume that she works...
Questions
question
Mathematics, 20.03.2020 12:06
question
Mathematics, 20.03.2020 12:06
question
Mathematics, 20.03.2020 12:06
question
Mathematics, 20.03.2020 12:06
Questions on the website: 13722361