On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,540,000. During 2021, costs of $2,180,000 were incurred with estimated costs of $4,180,000 yet to be incurred. Billings of $2,680,000 were sent, and cash collected was $2,430,000. In 2022, costs incurred were $2,680,000 with remaining costs estimated to be $3,870,000. 2022 billings were $2,930,000 and $2,655,000 cash was collected. The project was completed in 2023 after additional costs of $3,980,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.

Required:

1. Compute the amount of revenue and gross profit or loss to be recognized in 2021, 2022, and 2023 using the percentage of completion method.

2a. Prepare journal entries for 2021 to record the transactions described (credit "various

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 19:40
If w = 6 units, x = 3 units, and y = 5 units, what is the surface area of the figure? 168 units2 240 units2 144 units2 96 units2
Answers: 1
question
Mathematics, 21.06.2019 21:00
Kira looked through online census information to determine the overage number of people living in the homes in her city what is true about kira's data collection?
Answers: 1
question
Mathematics, 21.06.2019 23:00
Janie has $3. she earns $1.20 for each chore she does and can do fractions of chores. she wants to earn enough money to buy a cd for $13.50.
Answers: 1
question
Mathematics, 21.06.2019 23:30
In the equation sqrt(n+5)-sqrt(11-10)=1. what is the value of n
Answers: 1
You know the right answer?
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to b...
Questions
question
Mathematics, 16.07.2019 09:30
Questions on the website: 13722361