A project will take 720 person-days to complete. How many days will it take to complete the project if 5 people work on it?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:00
The axis of symmetry for the graph of the function f(x)=1/4^2+bx +10 is x=6. what is the value of b?
Answers: 1
question
Mathematics, 21.06.2019 20:00
M the table below represents a linear function f(x) and the equation represents a function g(x): x f(x)−1 −50 −11 3g(x)g(x) = 2x − 7part a: write a sentence to compare the slope of the two functions and show the steps you used to determine the slope of f(x) and g(x). (6 points)part b: which function has a greater y-intercept? justify your answer. (4 points)
Answers: 3
question
Mathematics, 21.06.2019 21:00
Meghan has created a diagram of her city with her house, school, store, and gym identified. a. how far is it from the gym to the store? b. meghan also wants to walk to get some exercise, rather than going to the gym. she decides to walk along arc ab. how far will she walk? round to 3 decimal places.
Answers: 2
question
Mathematics, 21.06.2019 21:20
Drag each expression to the correct location on the solution. not all expressions will be used. consider the polynomial 8x + 2x2 - 20x - 5. factor by grouping to write the polynomial in factored form.
Answers: 1
You know the right answer?
A project will take 720 person-days to complete. How many days will it take to complete the project...
Questions
question
Social Studies, 29.06.2019 17:40
Questions on the website: 13722367