you are planning to use PERT for planning of your project. A task has pessimistic estimate of 24 days, most likely estimate of 15 days and optimistic estimate of 12 days. what is the mean using the PERT technique
Answers: 2
Mathematics, 21.06.2019 14:50
What is [tex] {7}^{98 + \sqrt{4} } - 3 \times (64 \div 2 + 4 - 36) \times a = a + 36[/tex]?
Answers: 3
Mathematics, 21.06.2019 18:00
Li buys supplies so he can make and sell key chains. he begins to make a profit only after he sells 4 key chains. what point on the graph makes the most sense in this situation?
Answers: 2
Mathematics, 21.06.2019 20:00
Which of these tools or constructions is used to inscribe a hexagon inside a circle?
Answers: 1
Mathematics, 22.06.2019 00:00
What is the value of x in this triangle? a. 53° b. 62° c. 65° d. 118°
Answers: 2
you are planning to use PERT for planning of your project. A task has pessimistic estimate of 24 day...
English, 23.10.2020 17:00
Mathematics, 23.10.2020 17:00
History, 23.10.2020 17:00
Mathematics, 23.10.2020 17:00
English, 23.10.2020 17:00
Mathematics, 23.10.2020 17:00
Mathematics, 23.10.2020 17:00
Chemistry, 23.10.2020 17:00
History, 23.10.2020 17:00
Chemistry, 23.10.2020 17:00
Mathematics, 23.10.2020 17:00