A special machine is used at a construction site to dig holes. A hole is dug to a depth of 4.75 feet when the machine hits rock. The progress slows to 3/5 feet per hour of digging. The depth of the hole must be at least 12 1/2 feet by the end of the day to stay on schedule.
What is the minimum amount of time the machine must continue at its present rate to complete the hole on schedule?
Select from the drop-down menus to correctly complete the statement.
The machine requires at least
Choose...
hours and
Choose...
minutes to complete the hole on schedule.
Answers: 1
Mathematics, 21.06.2019 17:00
Find the value of the variable and the length of each secant segment.
Answers: 1
Mathematics, 21.06.2019 19:00
Lucy is a dress maker. she sews \dfrac47 7 4 of a dress in \dfrac34 4 3 hour. lucy sews at a constant rate. at this rate, how many dresses does lucy sew in one hour? include fractions of dresses if applicable
Answers: 3
Mathematics, 21.06.2019 20:20
Each person in an it department of 25 people works on at least one of 3 major projects: system security, program implementation, platform development. 10 people work on system security, 13 work on program implementation, and 12 work on platform development. 4 people work on system security and platform development, 5 people work on program implementation and platform development, and 2 people work on all three projects. how many people work on system security and program implementation?
Answers: 1
Mathematics, 21.06.2019 20:30
Is the point (0, 8) on the x-axis or y-axis? how do you know?
Answers: 2
A special machine is used at a construction site to dig holes. A hole is dug to a depth of 4.75 feet...
Mathematics, 29.04.2021 17:30
History, 29.04.2021 17:30
Biology, 29.04.2021 17:30
Mathematics, 29.04.2021 17:30
History, 29.04.2021 17:30
Mathematics, 29.04.2021 17:30
Mathematics, 29.04.2021 17:30
Physics, 29.04.2021 17:30
Social Studies, 29.04.2021 17:30