A project's completion time is uncertain and follows a normal distribution. The project has an expected completion time of 33 weeks, and with a project variance 12 weeks. The project manager wishes to determine the probability of finishing the project before the given deadline: 48 weeks from today. What is the corresponding z-value in determining the probability

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 13:30
Suppose a triangle has two sides of length 32 and 35, and that the angle between these two sides is 120°. which equation should you solve to find the length of the third side of the triangle?
Answers: 1
question
Mathematics, 21.06.2019 18:20
The total cost of anja’s trip to the dentist was $628.35. she paid a flat fee of $89.95 which included the checkup and cleaning and then had 4 cavities filled, each of which cost the same amount. which shows the correct equation and value of x, the cost of each cavity filling?
Answers: 2
question
Mathematics, 21.06.2019 19:00
Human body temperatures have a mean of 98.20° f and a standard deviation of 0.62°. sally's temperature can be described by z = 1.4. what is her temperature? round your answer to the nearest hundredth. 99.07°f 97.33°f 99.60°f 100.45°f
Answers: 1
question
Mathematics, 21.06.2019 19:20
Brainliest ! which of the coordinates are not of th vertices of the feasible region for the system of inequalities y≤4,,x≤5,x+y> 6 a(2,4) b(0,6) c(5,4) d(5,1)
Answers: 2
You know the right answer?
A project's completion time is uncertain and follows a normal distribution. The project has an expec...
Questions
question
Mathematics, 04.09.2020 05:01
question
Health, 04.09.2020 05:01
Questions on the website: 13722361