Question 4 (5 marks) To restore a vintage train, 13 activities need to be completed. The network below shows these 13 activities and their completion times in hours. C,6 G, 3 4,5 1D, 2 H,4 K,7 E, 2 L, 3 start finish B, 5 F,4 1,3 *M,6 J, 2 a. Determine the earliest starting time of activity F.

The minimum time in which all 13 activities can be completed is 21 hours.
b. What is the latest starting time of activity L?

C. What is the float time of activity J?

Just before they started restoring the train, the members of the club needed to add another activity, X, to the project Activity X will take seven hours to complete. Activity X has no predecessors, but must be completed before activity G starts.
d. What is the latest starting time of activity Xif it is not to increase the minimum completion time of the project? 1 mark​

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
Is fgh ~ jkl? if so, identify the similarity postulate or theorem that applies.
Answers: 1
question
Mathematics, 21.06.2019 17:30
Ineeeeed this is due tomorrow and i dont know the answer can you find all the exponents
Answers: 1
question
Mathematics, 21.06.2019 18:00
How do you solve a question like this?
Answers: 2
question
Mathematics, 21.06.2019 18:30
Water flows at a steady rate from a tap. its takes 40 seconds to fill a 4 litre watering can from the tap. the rate at which water flows from the tap is halved. complete: 4 litres into cm3
Answers: 3
You know the right answer?
Question 4 (5 marks) To restore a vintage train, 13 activities need to be completed. The network bel...
Questions
question
Mathematics, 04.01.2021 23:30
question
Mathematics, 04.01.2021 23:30
question
English, 04.01.2021 23:30
Questions on the website: 13722367