Invers proportion It take twelve workers tree weeks to complete four project.

Each project takes the same number of man-hours to complete.

a) t this rate, how long would it take fifteen workers to complete ten project? = 6 weeks

b) the ten project need to be completed in under four weeks. what is the minimum number of workers needed given that they a ll work at the s ame rate as the original workers? ( i know answer but in need xplaining ) :] B=D ( sorri ignore)
i have tutoring I Need this quickly

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 16:40
This question awards 100 ! i really don’t want to fail i will also mark you !
Answers: 2
question
Mathematics, 21.06.2019 21:00
Acomposition of transformations maps δxyz to δx"y"z". the first transformation for this composition is , and the second transformation is a 90° rotation about point x'.
Answers: 1
question
Mathematics, 21.06.2019 21:10
Mackenzie needs to determine whether the rectangles are proportional. which process could she use? check all that apply.
Answers: 1
question
Mathematics, 21.06.2019 21:30
Yesterday, george drank 1 small bottle and 2 large bottles, for a total of 1,372 grams. the day before , he drank 1 small bottle and 1 large bottle, for the total of 858 grams. how many grams does each bottle hold?
Answers: 1
You know the right answer?
Invers proportion It take twelve workers tree weeks to complete four project.

Each proj...
Questions
question
Mathematics, 06.05.2021 23:30
question
Mathematics, 06.05.2021 23:30
question
Mathematics, 06.05.2021 23:30
Questions on the website: 13722359