Mathematics, 09.08.2021 09:50 myamiller558

Invers proportion It take twelve workers tree weeks to complete four project.

Each project takes the same number of man-hours to complete.

a) t this rate, how long would it take fifteen workers to complete ten project? = 6 weeks

b) the ten project need to be completed in under four weeks. what is the minimum number of workers needed given that they a ll work at the s ame rate as the original workers? ( i know answer but in need xplaining ) :] B=D ( sorri ignore)
i have tutoring I Need this quickly

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 15:00
Which represents the inverse of the function f(x) = 4x? h(x) = x + 4 h(x) = x – 4 h(x) = x h(x) = x
Answers: 1
question
Mathematics, 21.06.2019 16:40
What are the solutions to the equation 4x2+3x=24-x
Answers: 2
question
Mathematics, 21.06.2019 21:00
Estimate the area under the curve f(x) = 16 - x^2 from x = 0 to x = 3 by using three inscribed (under the curve) rectangles. answer to the nearest integer.
Answers: 1
question
Mathematics, 21.06.2019 22:50
Use the quadratic function to predict f(x) if x equals 8. f(x) = 25x2 − 28x + 585
Answers: 1
You know the right answer?
Invers proportion It take twelve workers tree weeks to complete four project.

Each proj...
Questions
question
Biology, 01.12.2020 19:30
question
English, 01.12.2020 19:30
question
Mathematics, 01.12.2020 19:30
Questions on the website: 13722367