A can do a piece of work in 3 days and B in 6 days andShyam in 12 days. In how many days will they finish it when both work at it.​

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
The center of a circle represent by the equation (x+9)^2+(y-6)^2=10^2 (-9,6), (-6,9), (6,-9) ,(9,-6)
Answers: 1
question
Mathematics, 21.06.2019 17:50
The length and width of a rectangle are consecutive even integers the area of the rectangle is 120 squares units what are the length and width of the rectangle
Answers: 1
question
Mathematics, 21.06.2019 21:20
Amajor grocery store chain is trying to cut down on waste. currently, they get peaches from two different distributors, whole fruits and green grocer. out of a two large shipments, the manager randomly selects items from both suppliers and counts the number of items that are not sell-able due to bruising, disease or other problems. she then makes a confidence interval. is there a significant difference in the quality of the peaches between the two distributors? 95% ci for pw-pg: (0.064, 0.156)
Answers: 3
question
Mathematics, 21.06.2019 23:30
Without multiplying, tell which product is larger and why. 5 × 1/3 or 5 × 2/3 a)5 × 1/3 because 1/3 is less than 2/3 b) 5 × 1/3 because 1/3 is greater than 2/3 c) 5 × 2/3 because 1/3 is less than 23 d) 5 × 23 because 1/3 is greater than 2/3
Answers: 1
You know the right answer?
A can do a piece of work in 3 days and B in 6 days andShyam in 12 days. In how many days will they f...
Questions
question
Mathematics, 10.11.2020 21:50
question
Mathematics, 10.11.2020 21:50
question
Mathematics, 10.11.2020 21:50
question
Mathematics, 10.11.2020 21:50
Questions on the website: 13722367