A construction project is broken down into the following 10 activities: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
1 β€” 4
2 1 2
3 1 4
4 1 3
5 2, 3 5
6 3 6
7 4 2
8 5 3
9 6, 7 5
10 8, 9 7
b-1. Find the critical path.
1-3-5-8-10
1-2-5-8-10
1-3-6-9-10
1-4-7-9-10
b-2. How many weeks will the project take to complete?
c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which of the following options would reduce the project duration by four weeks? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)
Cut activity 3 by 3 weeks, and then reduce activity 6 or 9 by one week. unanswered
Cut activity 5 by 4 weeks. unanswered
Reduce activities 6 and 9 by a total of 3 weeks, and then reduce activity 3 by one week. unanswered
Cut activity 4 by 3 weeks, and then reduce activity 6 or 5 by one week. unanswered
Cut activity 5 by 3 weeks, and then reduce activity 4 or 9 by one week.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:00
Given that de, df, and ef are midsegments of β–³abc, and de=3.2 feet, ef=4 feet, and df=2.4 feet, the perimeter of β–³abc is .
Answers: 2
question
Mathematics, 21.06.2019 14:30
What is the volume of this square pyramid?
Answers: 2
question
Mathematics, 21.06.2019 15:50
Which of the following is the equation that says that the product of a number and ten is equal to 20 percent of that number ? a) 10n= 2.0n b) 10+n=.20n c) n+ .20n=10 d) 10n=0.20n
Answers: 1
question
Mathematics, 21.06.2019 16:00
Drag the tiles to the correct boxes to complete the pairs. not all tiles will be used. the heights of the girls in an advanced swimming course are 55, 60, 59, 52, 65, 66, 62, and 65 inches. match the measures of this data with their values.
Answers: 1
You know the right answer?
A construction project is broken down into the following 10 activities: ACTIVITY IMMEDIATE PREDECES...
Questions
question
Mathematics, 19.04.2020 08:31
question
Mathematics, 19.04.2020 08:32
Questions on the website: 13722361