The estimated project completion times ( days) for the Safaricom PLC Marketing research Assignment problem is as follows;
REGION
PROJECT LEADER 1 2 3
Muthoni 10 15 9
Oduor 9 18 5
Toroitich 6 14 3
Required:
1. Draw a network model for the project .
2. Develop the objective function
3. Conduct an optimal assignment of the three project leaders to the three regions using the Hungarian approach.
4. Comment on the results​
Answers: 1
Mathematics, 21.06.2019 19:40
Which of the following could be the ratio of the length of the longer leg 30-60-90 triangle to the length of its hypotenuse? check all that apply. a. 313 6 b. 3: 215 c. 18: 13 d. 1: 13 e. 13: 2 of. 3: 15
Answers: 3
Mathematics, 21.06.2019 20:10
Over which interval is the graph of f(x) = x2 + 5x + 6 increasing?
Answers: 1
The estimated project completion times ( days) for the Safaricom PLC Marketing research Assignment p...
Mathematics, 07.12.2020 14:00
Mathematics, 07.12.2020 14:00
Mathematics, 07.12.2020 14:00
Business, 07.12.2020 14:00
Mathematics, 07.12.2020 14:00
Mathematics, 07.12.2020 14:00
Mathematics, 07.12.2020 14:00
History, 07.12.2020 14:00
Mathematics, 07.12.2020 14:00
English, 07.12.2020 14:00
Mathematics, 07.12.2020 14:00
Mathematics, 07.12.2020 14:00
Business, 07.12.2020 14:00
Mathematics, 07.12.2020 14:00