5 people cleared a plot of land in 15 days. How many people would I need to hire to clear three times that plot in 5 days?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 20.06.2019 18:02
Cybil flips a coin and rolls a fair number cube at the same time. what is the probability that she will toss tails and roll a number less than 3?
Answers: 1
question
Mathematics, 21.06.2019 15:30
What is the value of y? round to the nearest tenth
Answers: 2
question
Mathematics, 21.06.2019 15:30
How many days was the temperature above 90 degrees?
Answers: 3
question
Mathematics, 21.06.2019 16:30
Why do interests rates on loans to be lower in a weak economy than in a strong one
Answers: 2
You know the right answer?
5 people cleared a plot of land in 15 days. How many people would I need to hire to clear three time...
Questions
question
Mathematics, 03.04.2021 18:00
question
Mathematics, 03.04.2021 18:00
question
Physics, 03.04.2021 18:00
Questions on the website: 13722360