0. 2074 Set B Q. No. 9a 20 men can do a piece of work in 24 days. After working for six days an additional number of men is employed to finish the work in 21 days from the beginning. Find the number of additional men. [3]​

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:00
After applying the composition r0.90 ry to rs what are the coordinates of r' and s'? a.r'(–3, 1),  s'(–3, 5)b.r'(–1, 3),  s'(–5, 3)c.r'(1, 3),  s'(5, 3)d.r'(5, 3),  s'(1, 3)
Answers: 2
question
Mathematics, 21.06.2019 17:00
For which of the following counts would a binomial probability model not be reasonable? a)the number of people in a classroom born in januaryb) the number of people in a classroom with red hair c) the number of people admitted to a hospital in a day with a particular disease d) the number of heart beats in a one-minute perio.
Answers: 3
question
Mathematics, 21.06.2019 19:00
Write a function for a rotation 90 degrees counter clockwise about the origin, point 0
Answers: 1
question
Mathematics, 21.06.2019 19:00
Find the y-intercept and x-intercept for the equation 5x-3y=60 what is the y-intercept
Answers: 1
You know the right answer?
0. 2074 Set B Q. No. 9a 20 men can do a piece of work in 24 days. After working for six days an addi...
Questions
question
Mathematics, 06.05.2021 16:40
question
Mathematics, 06.05.2021 16:40
question
Mathematics, 06.05.2021 16:40
question
English, 06.05.2021 16:40
question
Mathematics, 06.05.2021 16:40
question
Medicine, 06.05.2021 16:40
Questions on the website: 13722362