Para hacer 600 m de una obra, 30 obreros han trabajado 12 dias a razon de 10 horas diarias. ¿Cuantos dias necesitaran 36 obreros para hacer 900 m de la obra trabajando 6 horas diarias?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 12:30
Which expression is equivalent to (9x - 3 1/ + 1 3/8)
Answers: 1
question
Mathematics, 21.06.2019 19:00
Pyotr tchaikovsky sporting goods operates on a 45% overhead based on the selling price, which results in an overhead of $65.34 on the newest version of an air hockey game set. if the air hockey game set costs pyotr tchaikovsky sports $49.32, find the selling price, the markup, and the net profit.
Answers: 2
question
Mathematics, 21.06.2019 19:20
Which number completes the system of linear inequalities represented by the graph? y> 2x – 2 and x + 4y 2 et 2 3 4
Answers: 3
question
Mathematics, 21.06.2019 19:50
The probability that an adult possesses a credit card is .70. a researcher selects two adults at random. by assuming the independence, the probability that the first adult possesses a credit card and the second adult does not possess a credit card is:
Answers: 3
You know the right answer?
Para hacer 600 m de una obra, 30 obreros han trabajado 12 dias a razon de 10 horas diarias. ¿Cuantos...
Questions
question
Computers and Technology, 11.03.2021 09:00
question
Mathematics, 11.03.2021 09:00
question
Mathematics, 11.03.2021 09:00
question
Mathematics, 11.03.2021 09:00
Questions on the website: 13722367