If 12 assemblers can compleate a certain job in 6 hours, how long will the same job take if the number of assemblers is cut back to 9?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 18:00
If the cost to mail a package is an initial $5 and $0.28 for every pound the total cost to mail a package was $11.27, how much did the package weigh?
Answers: 1
question
Mathematics, 21.06.2019 19:00
Billy plotted −3 4 and −1 4 on a number line to determine that −3 4 is smaller than −1 4 .is he correct? explain why or why not
Answers: 3
question
Mathematics, 21.06.2019 20:30
In priyas math class there are 10 boys and 15 girls. what is the ratio of boys to girls in priyas math class? express your answer as a decimal
Answers: 1
question
Mathematics, 21.06.2019 22:20
F(x)=5/6x+3 which of the following is true
Answers: 1
You know the right answer?
If 12 assemblers can compleate a certain job in 6 hours, how long will the same job take if the numb...
Questions
question
Mathematics, 09.12.2021 02:20
Questions on the website: 13722359