subject
Mathematics, 28.05.2021 18:40 fish64

A project has the following activities and related data: Activity. Time (Weeks) Immediate Activity Predecessor Crash Most Most Most Cost Maximum Optimistic likely Pessimistic ($000) Crashable (a) (m) (C) per weeks week A None 1 3 11 3 1 00 None 4 5 6 4 1 С А 5 6 7 1 2 D А 4 5 12 1 2 1 E B 6 11 2 1 B 1 2 15 F 1 3 2 4 6 6 G CD 2 3 4 2 1 2 H EF G CD 2 4 6 6 N H EF 2 3 3 4 4 2 1 34a. (20 points) a. Compute the expected value E(t) and variance V(t) for all activities
Activity A B C D E F G H
E(t) weeks
V(t) weeks^2
b. there are three critical paths ACG, ADG, and BEH, all with expected project completion time time E(t) = 14 weeks. Compute the variance of project completion time for each path
V(ACG)=
V(ADG)=
V(BEH)
c. Assume that the project completion time T is normally distributed with mean E(T)=14 weeks and variance V(T) approximately by the maximum of the variances of the three individual critical paths. Determine the time X in weeks for which there is a 40% probability that the project can be completed on or before x.
d. List all alternatives and the respective costs for shortening the project by one week and identify the best alternative that has the minimum costs. Hint there are 8 alternatives
Alternative cost
the best alternative is..
e. For activity i, let Xi be the earliest finishing time and Yi be the number of weeks shortened. Formulate the linear program for minimizing the cost for shortening the project by one week

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 16:00
Pick the expression that matches this description: a polynomial of the 5th degree with a leading coefficient of 7 and a constant term of 6 (choice a) 7x^5+2x^2+6 (choice b) 7x^6−6x^4+5 (choice c) 6x^7−x^5+5 (choice d) 6x^5+x^4+7
Answers: 2
question
Mathematics, 21.06.2019 21:00
How to write four times a number,minus 6,is equal to theee times the number+8 as an equqtion
Answers: 2
question
Mathematics, 21.06.2019 22:30
How can you find the mean absolute deviation (mad) for this set of data?
Answers: 3
question
Mathematics, 21.06.2019 22:30
Assume that y varies inversely with x. if y=1.6 when x=0.5 find x when y=3.2 acellus answer
Answers: 2
You know the right answer?
A project has the following activities and related data: Activity. Time (Weeks) Immediate Activity P...
Questions
question
Biology, 10.02.2021 03:50
question
Mathematics, 10.02.2021 03:50
question
English, 10.02.2021 03:50
question
Mathematics, 10.02.2021 03:50
question
Mathematics, 10.02.2021 03:50
question
Mathematics, 10.02.2021 03:50
question
Mathematics, 10.02.2021 03:50
question
Mathematics, 10.02.2021 03:50
Questions on the website: 13722362