An automation project has the following activities and related data: Activity Time (Weeks)
Activity Immediate Predecessor Most Optimistic (a) Most likely (m) Most Pessimistic (c)
Crash Cost ($000) per week
Maximum Crashable weeks
A None 1 3 11 3 1
B None 4 5 6 4 1
C A 5 6 7 1 2
D A 4 5 12 1 2
E B 1 5 9 2 1
F B 1 2 15 3 1
G C, D, E 2 4 6 6 2
H F 2 3 4 2 1
13a. (10 points) Compute the Expected Value E(t) and Variance V(t) for all activities. (5 points deducted for any error).
13b. (10 points) There are three critical paths: ACG, ADG, and BEG, all with expected project completion time E(T)=14 weeks. Compute the variance of project completion time for each path.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:10
Can't gugys answer the ratio question. this is urgent the plans of a building is drawn toward scale of 1: 1000. kfc the foyer on the plans measures 62mm by 54mm, how large is the foyer in real life?
Answers: 1
question
Mathematics, 21.06.2019 19:30
Arestaurant chef made 1 1/2 jars of pasta sauce. each serving of pasta requires 1/2 of a jar of sauce. how many servings of pasta will the chef be able to prepare using the sauce?
Answers: 1
question
Mathematics, 21.06.2019 20:00
Combine like terms to make a simpler expression 3z+z
Answers: 2
question
Mathematics, 21.06.2019 22:00
There are 3232 forwards and 8080 guards in leo's basketball league. leo must include all players on a team and wants each team to have the same number of forwards and the same number of guards. if leo creates the greatest number of teams possible, how many guards will be on each team?
Answers: 2
You know the right answer?
An automation project has the following activities and related data: Activity Time (Weeks)
A...
Questions
question
Mathematics, 05.07.2019 22:00
Questions on the website: 13722367