When building a house, the number of days required to build is inversely proportional to with the number of workers. One house was built in 57 days by 6
workers. How many days would it take to build a similar house with 19 workers?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:40
Aline has a slope of and a y-intercept of –2. what is the x-intercept of the line?
Answers: 1
question
Mathematics, 21.06.2019 18:30
Do some research and find a city that has experienced population growth. determine its population on january 1st of a certain year. write an exponential function to represent the city’s population, y, based on the number of years that pass, x after a period of exponential growth. describe the variables and numbers that you used in your equation.
Answers: 3
question
Mathematics, 21.06.2019 22:20
Which graph represents the given linear function 4x+2y=3
Answers: 1
question
Mathematics, 22.06.2019 00:10
Answer asap and if you do you will get brainliest. catherine buys a gallon of ice cream from the store. after taking it home, she eats a fifth of a gallon of ice cream. her sister eats some of the ice cream as well. if two-thirds of the original amount of ice cream is left, then what fraction of a gallon of ice cream did her sister eat?
Answers: 2
You know the right answer?
When building a house, the number of days required to build is inversely proportional to with the n...
Questions
question
Mathematics, 20.08.2021 02:20
question
Mathematics, 20.08.2021 02:20
question
Mathematics, 20.08.2021 02:20
question
Mathematics, 20.08.2021 02:20
question
History, 20.08.2021 02:20
question
Mathematics, 20.08.2021 02:20
question
Mathematics, 20.08.2021 02:20
question
Mathematics, 20.08.2021 02:20
question
Mathematics, 20.08.2021 02:20
Questions on the website: 13722363