Completion time (from start to finish) of a building remodeling project is normally distributed with a mean of 200 work days and a standard deviation of 10 workdays. To be 99% sure that you will not be late in completing the project, you should request a completion time of workdays.

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 14:40
Which statement most accurately describe why the division property of exponents does not apply to the expression (-8)^2/(-3)^4
Answers: 2
question
Mathematics, 21.06.2019 20:30
Carley bought a jacket that was discounted 10% off the original price. the expression below represents the discounted price in dollars, based on x, the original price of the jacket.
Answers: 1
question
Mathematics, 21.06.2019 23:00
If i purchase a product for $79.99 and two accessories for 9.99 and 7.00 how much will i owe after taxes applies 8.75%
Answers: 2
question
Mathematics, 22.06.2019 02:30
The gdp is $1,465.2 billion. the population is 249,793,675. find the per capita gdp.
Answers: 1
You know the right answer?
Completion time (from start to finish) of a building remodeling project is normally distributed with...
Questions
question
Mathematics, 19.10.2021 03:40
question
Social Studies, 19.10.2021 03:40
question
Mathematics, 19.10.2021 03:40
question
Mathematics, 19.10.2021 03:40
Questions on the website: 13722367