The following is a linear programming formulation of a labor planning problem. There are four overlapping shifts, and management must decide how many employees to schedule to start work on each shift. The objective is to minimize the total number of employees required while the constraints stipulate how many employees are required at each time of day. The variables X1 - X4 represent the number of employees starting work on each shift (shift 1 through shift 4). MIN X1 + X2 + X3 + X4

s. t. X1 + X4 ≥ 12 (on duty during shift 1)
X1 + X2 ≥ 15 (on duty during shift 2)
X2 + X3 ≥ 16 (on duty during shift 3)
X3 + X4 ≥ 14 (on duty during shift 4)
X1, X2, X3, and X4 ≥ 0

Given the optimal solution: X1* = 13, X2* = 2, X3* = 14, X4* = 0, how many workers would be assigned to shift 2?

a. 13
b. 12
c. 14
d. 15
e. 2

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 19:30
Si la base de un triángulo isósceles mide 70 m y el ángulo opuesto a ésta mide 58°; entonces ¿cuánto mide la altura de dicho triángulo? a) 21.87 m. b) 40.01 m. c) 43.74 m. d) 63.14 m.
Answers: 1
question
Mathematics, 21.06.2019 19:30
In the geometric progression –3, 12, −48… what term is 3,072?
Answers: 2
question
Mathematics, 21.06.2019 23:50
The graph of a curve that passes the vertical line test is a:
Answers: 3
question
Mathematics, 22.06.2019 00:30
Which of the following is the sum of 3 1/6 + 6 3/8?
Answers: 2
You know the right answer?
The following is a linear programming formulation of a labor planning problem. There are four overla...
Questions
question
Advanced Placement (AP), 20.04.2021 18:50
question
Mathematics, 20.04.2021 18:50
question
Mathematics, 20.04.2021 18:50
question
Social Studies, 20.04.2021 18:50
Questions on the website: 13722367