18 men can do a piece of work in 15 days. How many more men are needed if the work is to be completed in 10 days​

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:00
The classrooms are trying to raise $1,200.00 for charity. mrs. leblanc's class has raised 50%. mr. patel's class has raised $235.14 ms. warner's class has raised 1/3 as much as mrs. leblanc's class. how much more money is needed to reach the goal of $1,200.00?
Answers: 1
question
Mathematics, 21.06.2019 17:00
Acylinder has volume 45π and radius 3. what is it’s height?
Answers: 2
question
Mathematics, 21.06.2019 18:30
Aball is thrown from a height of 139 feet with an initial downward velocity of 15 ft/s. the ball's height h (in feet) after t seconds is given by the following. h=139-15t-16t^2 how long after the ball is thrown does it hit the ground? round your answer(s) to the nearest hundredth. (if there is more than one answer, use the "or" button.) t =
Answers: 1
question
Mathematics, 21.06.2019 21:00
To finance her community college education, sarah takes out a loan for $2900. after a year sarah decides to pay off the interest, which is 4% of $2900. how much will she pay
Answers: 1
You know the right answer?
18 men can do a piece of work in 15 days. How many more men are needed if the work is to be complete...