Processing times and due dates of 9 jobs are given as follows: Job 1 2 3 4 5 6 7 8 9
Proc Time 4 3 7 9 8 15 6 7 10
Due Date 35 40 44 25 20 43 40 22 38
Assume that all jobs arrive at time 0
a) Generate a schedule that minimizes the mean flow time. Break ties with the smallest job number first (i. e., if 3 and 8 have identical parameters, 3 should be scheduled first).
b) Calculate mean flow time, mean tardiness, and maximum tardiness of the schedule obtained in a)
c) Generate a schedule that minimizes the maximum tardiness. Break ties with the smallest job number first.
d) Calculate mean flow time, mean tardiness, and maximum tardiness of the schedule obtained in c)

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 20.06.2019 18:04
Medium sodas cost $1.25 and hot dogs cost $2.50. natalie’s group brought in pizzas but is buying the drinks at concession stand. how many medium sodas can natalie’s group buy with $20? make a table to show answer.
Answers: 1
question
Mathematics, 21.06.2019 18:00
Calculate the density of benzene if 300ml of it weighs 263g. a. 0.88 g/ml b. 1.14 g/ml c. 78,900 g/ml d. 37 g/ml
Answers: 2
question
Mathematics, 21.06.2019 19:30
Complete the solution of the equation. find the value of y when x equals to 1 9x-5y=29
Answers: 2
question
Mathematics, 21.06.2019 21:30
Handsome jack is buying a pony made of diamonds. the price of the pony is p dollars, and jack also has to pay a 25% diamond pony tax. which of the following expressions could represent how much jack pays in total for the pony?
Answers: 1
You know the right answer?
Processing times and due dates of 9 jobs are given as follows: Job 1 2 3 4 5 6 7 8 9
Proc Ti...
Questions
question
Social Studies, 17.10.2020 04:01
question
Mathematics, 17.10.2020 04:01
question
Mathematics, 17.10.2020 04:01
question
Social Studies, 17.10.2020 04:01
question
Chemistry, 17.10.2020 04:01
Questions on the website: 13722367