There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2. what is the probability that the project will be completed in 38 weeks if its expected completion time is 40 weeks?
Answers: 1
Mathematics, 21.06.2019 14:30
Write the system of equations represented by the matrix. 0 1 2 4 -2 3 6 9 1 0 1 3
Answers: 2
Mathematics, 21.06.2019 20:30
26) -2(7x) = (-2 ā¢ 7) x a. associative property of addition b. associative property of multiplication c. commutative property of multiplication d. commutative property of addition
Answers: 1
Mathematics, 21.06.2019 21:40
Astudy was interested in determining if eating milk chocolate lowered someone's cholesterol levels.ten people's cholesterol was measured. then, each of these individuals were told to eat 100g of milk chocolate every day and to eat as they normally did. after two weeks, their cholesterol levels were measured again. is there evidence to support that their cholesterol levels went down? how should we write the alternative hypothesis? (mud = the population mean difference= before - after)a. ha: mud = 0b. ha: mud > 0c. ha: mud < 0d. ha: mud does not equal 0
Answers: 1
There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2....
Mathematics, 20.04.2021 08:30
Mathematics, 20.04.2021 08:30
Mathematics, 20.04.2021 08:30
Mathematics, 20.04.2021 08:30
Mathematics, 20.04.2021 08:30
Mathematics, 20.04.2021 08:40
English, 20.04.2021 08:40
Mathematics, 20.04.2021 08:40