Company alpha can produce 500 desks in 3 days while company beta can produce 700 desks in 4 days. if the two companies join forces, how many days would it take them to produce 3000 desks?
about 7 days
about 9 days
about 11 days
about 13 days
pump 1 can empty a pool in 5 hours while pump 2 can empty the same pool in 9 hours. if the two pumps were to work together, how long would it take them to empty the pool? about 3 hours
about 3 hours and 15 minutes
about 3 hours and 30 minutes
about 3 hours and 45 minutes

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 20.06.2019 18:04
Atriangle has sides with lengths of 10 yards, 13 yards, and 18 yards. is it a right triangle?
Answers: 1
question
Mathematics, 21.06.2019 15:00
What are the relative frequencies to the nearest hundredth of the columns of the two-way table?
Answers: 2
question
Mathematics, 21.06.2019 18:00
What is the location of point g, which partitions the directed line segment from d to f into a 5: 4 ratio? –1 0 2 3
Answers: 1
question
Mathematics, 22.06.2019 00:40
Can you divide 25 into 4 equal groups? explain why or why not.
Answers: 1
You know the right answer?
Company alpha can produce 500 desks in 3 days while company beta can produce 700 desks in 4 days. if...
Questions
question
History, 26.11.2019 19:31
Questions on the website: 13722367