Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24 and the probability of finishing by day 21. (Round your intermediate calculations to 3 decimal places and final answers to 4 decimal places.)

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 13:20
Which equation can be used to solve for the unknown number? seven less than a number is thirteen. n-7=13 7-n=13 n+7=13 n+13=7
Answers: 1
question
Mathematics, 22.06.2019 00:30
How can you find the magnitude of a vector, v = < x,y > , where the horizontal change is x and the vertical change is y?
Answers: 1
question
Mathematics, 22.06.2019 04:00
Solve one step and two step problems
Answers: 1
question
Mathematics, 22.06.2019 04:30
When 60% of a number is added to the number the result is 192 what is the bumber
Answers: 1
You know the right answer?
Suppose it is now the end of the seventh day and that activities A and B have been completed while a...
Questions
question
Mathematics, 25.02.2021 20:00
Questions on the website: 13722363