Engineers are digging a 3200-foot-long tunnel at a constant rate. After 5 months, the engineers still need to dig 1700 feet to finish the project. How much time does it take to complete the tunnel from start to finish? Will the engineers have enough time if the project was started in December 2020 and the deadline to finish the project was in August 2021? Please explain your answer for yes or no.

Hint:
y=mx+b (slope-intercept form)
x=time
y=distance
b=3200
Start & Finish: ??
Total length=3200ft
Left over=1700ft after 5 months of digging

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 17:30
Select the correct answer from the drop-down menu. subtracting 3xy^2 from 8xy^2 gives the same result as the expression. [tex]3xy ^{2} - 8xy ^{2} [/tex][tex] { - 7xy}^{2} - {2xy}^{2} [/tex][tex] {7xy}^{2} - {2xy}^{2} [/tex]
Answers: 3
question
Mathematics, 21.06.2019 18:00
Simplify the expression. -2/5(10+15m-20n)
Answers: 1
question
Mathematics, 21.06.2019 19:00
If f(x)= sqrt4x+9+2, which inequality can be used to find the domain of f(x)?
Answers: 2
question
Mathematics, 21.06.2019 21:00
How do i put 3(x+7) in distributive property
Answers: 2
You know the right answer?
Engineers are digging a 3200-foot-long tunnel at a constant rate. After 5 months, the engineers stil...
Questions
question
Mathematics, 17.11.2020 03:40
question
Mathematics, 17.11.2020 03:40
question
Engineering, 17.11.2020 03:40
question
Mathematics, 17.11.2020 03:40
question
History, 17.11.2020 03:40
question
English, 17.11.2020 03:40
question
Mathematics, 17.11.2020 03:40
Questions on the website: 13722367