Mathematics, 23.03.2021 03:50 ThatOneDumbAsian

The time required to complete a job varies inversely as the number of people working. It took 3 hours for 8 electricians to wire a building. How long would it have taken 6 electricians to do the job?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 17:30
What is the greater volume 72 quarts or 23 gallons
Answers: 1
question
Mathematics, 21.06.2019 18:00
Arecipe calls for 32 fluid ounces of heavy cream.how many 1 pint containers of heavy cream are needed to make the recipe?
Answers: 2
question
Mathematics, 21.06.2019 19:10
Do more republicans (group a) than democrats (group b) favor a bill to make it easier for someone to own a firearm? two hundred republicans and two hundred democrats were asked if they favored a bill that made it easier for someone to own a firearm. how would we write the alternative hypothesis?
Answers: 1
question
Mathematics, 21.06.2019 19:30
You deposit $5000 each year into an account earning 3% interest compounded annually. how much will you have in the account in 30 years?
Answers: 3
You know the right answer?
The time required to complete a job varies inversely as the number of people working. It took 3 hou...
Questions
question
Mathematics, 15.11.2019 04:31
question
History, 15.11.2019 04:31
question
Engineering, 15.11.2019 04:31
question
Mathematics, 15.11.2019 04:31
Questions on the website: 13722367