Consider a simple two-stage assembly line that has two identical robot arms (one for each stage).The system is functioning if a part can receive processing (i. e. the robot arm is working) in bothstages of an assembly line. Your supervisor knows that a pure series system is not the most reliable and has authorized the purchase of two additional arms to be used to add redundancy to the system. However, she is unsure of the best way to set up the additional components to maximize system reliability. There are two options being considered: 1. Put an additional arm in each stage so that the arms in a single stage operate in parallel.
2. Set up an additional two-stage assembly line that will operate in parallel with the original line. Assume the individual component reliability for all 4 arms is R.

a. What is the system reliability of the first option in terms of R?
b. What is the system reliability of the second option in terms of R?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 19:00
John used linear combination to solve the system of equations shown. he did so by multiplying the first equation by -3 and the second equation by another number to eliminate the x-terms. what number did jonas multiply the second equation by? 4x-6y=23x+5y=11
Answers: 2
question
Mathematics, 21.06.2019 19:30
Atemperature of 1.64â—¦f corresponds to answer in units of â—¦c.
Answers: 1
question
Mathematics, 21.06.2019 21:00
With alll of except for the 2 that i did already
Answers: 1
question
Mathematics, 21.06.2019 23:30
Select the correct answer and solve for y
Answers: 2
You know the right answer?
Consider a simple two-stage assembly line that has two identical robot arms (one for each stage).The...
Questions
question
Mathematics, 24.09.2019 13:00
question
Mathematics, 24.09.2019 13:00
question
English, 24.09.2019 13:00
question
Chemistry, 24.09.2019 13:00
Questions on the website: 13722361