DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month
1 2 3 4
Throughput time (days) ? ? ? ?
Delivery cycle time (days) ? ? ? ?
Manufacturing cycle efficiency (MCE) ? ? ? ?
Percentage of on-time deliveries 78 % 73 % 70 % 67 %
Total sales (units) 2330 2230 2116 2036
Management has asked for your help in computing throughput time, delivery cycle time, and MCE. The following average times have been logged over the last four months:
Average per Month (in days)
1 2 3 4
Move time per unit 0.8 0.4 0.5 0.5
Process time per unit 3.4 3.2 3.0 2.8
Wait time per order before start of production 23.0 25.2 30.0 32.3
Queue time per unit 4.3 5.1 6.0 7.0
Inspection time per unit 0.6 0.9 0.9 0.6
Required:
1-a. Compute the throughput time for each month.
1-b. Compute the delivery cycle time for each month.
1-c. Compute the manufacturing cycle efficiency (MCE) for each month.
2. Evaluate the company’s performance over the last four months.
3-a. Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as in month 4, except that through the use of Lean Production the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE.
3-b. Refer to the move time, process time, and so forth, given for month 4. Assume in month 6 that the move time, process time, and so forth, are again the same as in month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE.

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 13:00
In the diagram below, dab and dac are adjacent angles. if mdac = 25°, what is mdab in degrees? what is mbac in degrees?
Answers: 3
question
Mathematics, 21.06.2019 20:00
One hectometer is a) 1/1000 of a meter. b) 1/100 of a meter. c) 10 meters. d) 100 meters. e) 1000 meters.
Answers: 1
question
Mathematics, 22.06.2019 01:00
Multiply and simplify. 2x2y3z2 · 4xy4x2 how to do?
Answers: 1
question
Mathematics, 22.06.2019 05:40
For a short time after a wave is created by wind , the height of the wave can be modeled using y= a sin 2pi(t) / t where a is the amplitude and t is the period of the wave in seconds. how many times over the first 5 seconds does the graph predict the wave to be 2 feet high?
Answers: 1
You know the right answer?
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufa...
Questions
Questions on the website: 13722361