7070 To complete a task in 16 days a company needs
5 people each working for 6 hours per day.
The company decides to have
8 people each working for 4 hours per day.
Assuming that each person works at the same rate,
how many days will the task take to complete?
o

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
Wanna brainliest? ! ms. mcmahon is building a shed as shown. what is the measure of the angle at the top of the shed? a) 126 b )116 c) 64 d) 32
Answers: 1
question
Mathematics, 21.06.2019 18:40
The table shows the results of three plays in a football game. what is the net result of the three plays? football game 1st play 5 yards 2nd play -9 yards 3rd play 12 yards
Answers: 2
question
Mathematics, 21.06.2019 23:30
Ahighway between points a and b has been closed for repairs. an alternative route between there two locations is to travel between a and c and then from c to b what is the value of y and what is the total distance from a to c to b?
Answers: 1
question
Mathematics, 22.06.2019 00:00
In a timed typing test lara typed 63 words per minute.estimate the number of words she should be able to type in half in hour show your work
Answers: 2
You know the right answer?
7070 To complete a task in 16 days a company needs
5 people each working for 6 hours per day....
Questions
question
Mathematics, 27.03.2021 05:20
question
Mathematics, 27.03.2021 05:20
question
Mathematics, 27.03.2021 05:20
question
Mathematics, 27.03.2021 05:20
question
Mathematics, 27.03.2021 05:20
Questions on the website: 13722363