709 To complete a task in 16 days a company needs
5 people each working for 6 hours per day.
The company decides to have
8 people each working for 4 hours per day.
Assuming that each person works at the same rate,
how many days will the task take to complete?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 18:30
41/17 as a decimal rounded to the nearest hundredth
Answers: 1
question
Mathematics, 21.06.2019 21:00
In the figure below, triangle rpq is similar to triangle rts. what is the distance between p and q? a. 24 b. 42 c.50 d. 54
Answers: 1
question
Mathematics, 21.06.2019 23:00
What is the value of x in the equation7x+2y=48 when y=3
Answers: 2
question
Mathematics, 22.06.2019 03:50
Question 2 of 102 pointsthe temperature is 45°f. the temperature will decrease by 2°f each hour. leth be the number of hours.when will the temperature be below 32°f? write an inequality for this problem.oa. 45 + 2h 32b. 45 + 2h< 32o c. 45 - 2h< 32od. 45 - 2hs 32
Answers: 2
You know the right answer?
709 To complete a task in 16 days a company needs
5 people each working for 6 hours per day.<...
Questions
question
Social Studies, 10.06.2021 18:00
question
Mathematics, 10.06.2021 18:00
Questions on the website: 13722362