When building a house, the number of days required to build varies inversely with with the number of workers. One house was built in 29 days by 27 workers. How many days would it take to build a similar house with 9 workers?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 18:00
Oscar and julie ashton are celebrating their 15th anniversary by having a reception hall. they have budgeted $4,500 for their reception. if the reception hall charges a $90 cleanup fee plus & 36 per person, find the greatest number of people that they may invite and still stay within their budget.
Answers: 1
question
Mathematics, 21.06.2019 19:30
Suppose i pick a jelly bean at random from a box containing one red and eleven blue ones. i record the color and put the jelly bean back in the box. if i do this three times, what is the probability of getting a blue jelly bean each time? (round your answer to three decimal places.)
Answers: 1
question
Mathematics, 21.06.2019 19:40
Which system of linear inequalities is represented by the graph?
Answers: 1
question
Mathematics, 21.06.2019 20:30
Write two point-slope equations for the line passing through the points (6, 5) and (3, 1)
Answers: 1
You know the right answer?
When building a house, the number of days required to build varies inversely with with the number of...
Questions
question
Mathematics, 12.03.2021 03:10
question
Mathematics, 12.03.2021 03:10
question
Social Studies, 12.03.2021 03:10
Questions on the website: 13722363