Mathematics, 15.02.2021 21:30 cinthyafleitas

A rubber-tired scraper with an efficiency of 52 min/hr has a heaped capacity of 26 cu yd. If it is to move material with a swell factor of 24%, what amount of in-bank material can it move in 1 hour, assuming it has a total cycle time of 6 minutes?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
Iwill give brainliest only if your correct the words subsequent and submerge both contain the prefix sub. based on this information, what does the prefix sub most likely mean? a) under or secondary b) true or verifiable c) tricky or difficult d) around or centered on
Answers: 1
question
Mathematics, 21.06.2019 16:30
The angles below are supplementary. what is the value of x? a pair of supplementary angles is shown. one angle measures 7x + 33, and the other angle measures 70. 5.3 8.14 11 14.7
Answers: 1
question
Mathematics, 21.06.2019 16:50
An angle that measures between 90 and 180° is called a(,
Answers: 2
question
Mathematics, 21.06.2019 20:10
Ascientist has discovered an organism that produces five offspring exactly one hour after its own birth, and then goes on to live for one week without producing any additional offspring. each replicated organism also replicates at the same rate. at hour one, there is one organism. at hour two, there are five more organisms. how many total organisms are there at hour seven? 2,801 19,531 19,607 97.655
Answers: 1
You know the right answer?
A rubber-tired scraper with an efficiency of 52 min/hr has a heaped capacity of 26 cu yd. If it is t...
Questions
question
Chemistry, 10.12.2020 03:30
question
Mathematics, 10.12.2020 03:30
question
Mathematics, 10.12.2020 03:30
Questions on the website: 13722362