To complete a task in 15 days, a company has 4 people each working 8 hours a day. The company
decide to have 5 people each working 6 hours a day. Assume that each person works at the same
rate.
a) How many days will it take the 5 people to complete the task?
b)Comment on how the assumption affects your answer to part (a).
Answers: 2
Mathematics, 21.06.2019 21:30
The measures of the legs of a right triangle are 15m and 20m . what is the length of the hypotenuse
Answers: 1
Mathematics, 21.06.2019 23:30
What is the simplified form of square root of 400 to the 100th power ?
Answers: 1
Mathematics, 21.06.2019 23:30
Line u passes through points (-52, -18) and (-29, 53). line v passes through points (90, 33) and (19, 56). are line u and line v parallel or perpendicular?
Answers: 1
Mathematics, 22.06.2019 01:00
Multiply: 2.7 Ć (ā3) Ć (ā1.2). a. ā9.72 b. ā10.8 c. 10.8 d. 9.72
Answers: 2
To complete a task in 15 days, a company has 4 people each working 8 hours a day. The company
decid...
History, 11.12.2019 07:31
Computers and Technology, 11.12.2019 07:31
History, 11.12.2019 07:31
Mathematics, 11.12.2019 07:31
Mathematics, 11.12.2019 07:31
Mathematics, 11.12.2019 07:31
Business, 11.12.2019 07:31
Mathematics, 11.12.2019 07:31
English, 11.12.2019 07:31
Chemistry, 11.12.2019 07:31
Mathematics, 11.12.2019 07:31
Physics, 11.12.2019 07:31
Social Studies, 11.12.2019 07:31