On a certain workday, the rate, in tons per hour, at which unprocessed gravel arrives at a gravel processing plant is
modeled by G(t) = 90 + 45 cos (t), where t is
measured in hours and 0 the workday (t=0), the plant has 500 tons of unprocessed
gravel. During the hours of operations, 0 plant processes gravel at a constant rate of 100 tons per
hour.
d.) what is the maximum amount of unprocessed gravel
at the plant during the hours of operation on this
workday. Justify your answer.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 19:10
How many solutions does the nonlinear system of equations graphed below have?
Answers: 2
question
Mathematics, 21.06.2019 22:10
Akitchen is 12 ft. by 14 ft. with 10 ft. high walls. how much would it cost to put vinyl flooring in this room? $8.80 per ft
Answers: 1
question
Mathematics, 22.06.2019 00:30
Simplify the algebraic expression 8y-2(y+4)
Answers: 2
question
Mathematics, 22.06.2019 02:00
Add. express your answer in simplest form. 12 9/10+2 2/3 = i need u guys to me find the answer to this question
Answers: 1
You know the right answer?
On a certain workday, the rate, in tons per hour, at which unprocessed gravel arrives at a gravel p...
Questions
question
English, 20.10.2020 16:01
question
Mathematics, 20.10.2020 16:01
question
English, 20.10.2020 16:01
question
Chemistry, 20.10.2020 16:01
Questions on the website: 13722367