If 5 workers complete one task in 7 days, then how many days will 7 workers take to complete the same task?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 20.06.2019 18:04
George is 187 cm tall. his son, ralph, is 142 cm tall. who casts the longer shadow. george when the sun is 65° above the horizon, or ralph when the sun is 56° above the horizon? how much longer? (nearest centimeter)
Answers: 2
question
Mathematics, 21.06.2019 13:40
Show algebraically that f and g are inverse functions f(x)=x^2/-6; g(x)=square root of 2x+12
Answers: 1
question
Mathematics, 21.06.2019 19:10
Click an item in the list or group of pictures at the bottom of the problem and, holding the button down, drag it into the correct position in the answer box. release your mouse button when the item is place. if you change your mind, drag the item to the trashcan. click the trashcan to clear all your answers. solve this quadratic equation using the quadratic formula. 2x2 - 2x=1 need asap
Answers: 2
question
Mathematics, 21.06.2019 20:00
Given ab and cb are tangents of p, and m =10°. what is the measure of abp?
Answers: 1
You know the right answer?
If 5 workers complete one task in 7 days, then how many days will 7 workers take to complete the sam...
Questions
question
Mathematics, 20.10.2019 03:00
question
Chemistry, 20.10.2019 03:10
question
Health, 20.10.2019 03:10
Questions on the website: 13722360